Development Application MCUI/44/2024 – Key Assessment Timeline

Place of Worship and Community Use

283–293 Logan Reserve Road, Logan Reserve

Key milestones from lodgement through to formal Council approval

Date Milestone
27 June 2024 Development Application submitted to Logan City Council
7 August 2024 Confirmation Notice issued; application formally entered assessment
23 August 2024 Information Request issued; flooding identified as primary threshold issue
28 August 2024 Action plan confirmed to prioritise flood modelling
30 September 2024 Online meeting held to discuss flood strategy
Sept – Nov 2024 Specialist flood modelling undertaken and design refined
19 November 2024 Meeting with Council to review flood modelling outcomes
18 December 2024 Council provided final guidance on flood hazard classifications
January 2025 Progression to remaining Information Request items
6 March 2025 Response to Request for Information submitted to Council
19 March – 9 April 2025 Public notification period as per the Planning Act 2016
1 May 2025 Request for Information received
16 May 2025 Further Request for Information received
3 June 2025 Further Request for Information received
29 August 2025 Response to Request for Information on acoustics-related matters
11 September 2025 Response to further Requests for Information (1 May, 16 May, 3 June 2025) submitted to Council
December 2025 Council commenced preparation of draft development conditions
18 December 2025 Council required Community Hall delivery in Stage 1 (single-staged development)
22–24 December 2025 Agreement reached on Stage 1 Community Hall delivery
7–9 January 2026 Council confirmed draft conditions and Councillor consultation
15 January 2026 Draft development conditions issued
16–19 January 2026 Preferred operating hours confirmed; acoustic amendment approved
21–22 January 2026 Detailed condition-by-condition feedback submitted
30 January 2026 Council responded on acoustic conditions
4 February 2026 110-person event threshold formally agreed
13 March 2026 Committee-based determination pathway confirmed
25 March 2026 All condition amendments resolved; assessment complete
15 April 2026 Application considered by Council’s City Planning Committee and referred to the full Council meeting
22 April 2026 Full Council meeting deferred the decision on the DA to a future meeting
10 June 2026 Development application assessed and recommended for approval by the City Shape, Economic Transformation & Transport Committee of Logan City Council (Council Minute No. 98/2026)
17 June 2026 Approved by Logan City Council’s full Council meeting (Council Meeting Minute No. 98/2026)
23 June 2026 Formal Decision Notice issued by Logan City Council

Note: The Material Change of Use component of this approval has a currency period of 6 years and remains subject to the statutory appeal period under the Planning Act 2016.