The following is the key timeline and major milestone dates.
| 1. | Registration of Queensland Nepalese Community Centre Inc. | : | 27 April 2018 |
| 2. | Official Name Change to Queensland Nepalese Cultural Centre | : | 26 April 2018 |
| 3. | Execution of Property Purchase Contract | : | 12 June 2023 |
| 4. | Milestone: Reached 500 Life Members | : | 20 September 2023 |
| 5. | Property Settlement and Title Transfer | : | 16 October 2023 |
| 6. | Ratification of Revised QNCC Constitution | : | 28 May 2024 |
| 7. | Submission of Development Application (DA) | : | 31 July 2024 |
| 8. | Receipt of First Request for Information (RFI) from Council | : | 22 August 2024 |
| 9. | Submission of Response to First RFI | : | 6 March 2025 |
| 10. | Commencement of Public Notification Period | : | 18 March 2025 |
| 11. | Receipt of Subsequent RFIs from Logan City Council | : | 1 May 2025, 16 May 2025 & 3 June 2025 |
| 12. | Submission of Response to Second Round of RFIs | : | 11 September 2025 |
| 13. | Receipt of Draft DA Conditions | : | 15 January 2026 |
| 14. | Submission of Requested Amendments to Draft Conditions | : | 22 January 2026 |
| 15. | Decision of DA (Anticipated) | : | April 2026 |