1.Registration of Queensland Nepalese Community Centre Inc.:27 April 2018
2.Official Name Change to Queensland Nepalese Cultural Centre:26 April 2018
3.Execution of Property Purchase Contract:12 June 2023
4.Milestone: Reached 500 Life Members:20 September 2023
5.Property Settlement and Title Transfer:16 October 2023
6.Ratification of Revised QNCC Constitution:28 May 2024
7.Submission of Development Application (DA):31 July 2024
8.Receipt of First Request for Information (RFI) from Council:22 August 2024
9.Submission of Response to First RFI:6 March 2025
10.Commencement of Public Notification Period:18 March 2025
11.Receipt of Subsequent RFIs from Logan City Council:1 May 2025, 16 May 2025 & 3 June 2025
12.Submission of Response to Second Round of RFIs:11 September 2025
13.Receipt of Draft DA Conditions:15 January 2026
14.Submission of Requested Amendments to Draft Conditions:22 January 2026
15.Decision of DA (Anticipated):April 2026